Project Update - May 27, 2025
Below is a summary of construction activities for this week and a preview of planned work for next week. Please note that schedules may shift due to weather. Weekly updates will continue to keep you informed.
This Week - Week of May 26
Mission Area:
- Pouring of new concrete curb and gutter (see note below)
- Asphalt patching
- Topsoil and vegetation restoration
- Private utility relocations
Seven Greens/Silverthorne Area:
- Private utility relocations
6th Avenue:
- Replacement of damaged city utilities such as water valves (see note below)
- Private utility relocations
Looking Ahead - Week of June 2
Mission Area:
Seven Greens/Silverthorne Area:
- Private utility relocations
6th Avenue:
- Pouring of new concrete curb and gutter
- Replacement of damaged city utilities such as water valves
- Private utility relocations
Additional Information
Water Outage Notice – Mission and 6th Avenue Areas
Some properties in the Mission and 6th Avenue areas will experience a 6-8 hour water outage during utility replacement work. Affected residents will receive a paper notice with additional details and anticipated outage times for each property.
Note about Newly Poured Concrete
Newly poured concrete curb and gutter should not be driven on for 7 days. Residents in the Mission and 6th Avenue areas are allowed to park on the street if needed during this time.
For construction-related questions, residents can contact Matt Tang, Plymouth’s construction representative, at MTang@plymouthmn.gov or 763-509-5529.
Below is a list of project update eNotify emails that have been sent to subscribers of the 2025 Street Rehabilitation Project. Subscribe online to receive the emails.
- 2025 Street Rehabilitation Project updates for the weeks of May 26 and June 2 - May 27, 2025
- 2025 Street Rehabilitation Project updates for the weeks of May 19 and 26 - May 20, 2025
- 2025 Street Rehabilitation Project update for the weeks of May 12 and 19 - May 13, 2025
- 2025 Street Rehabilitation Project update about through traffic closures - May 8, 2025
- 2025 Street Rehabilitation Project update about curb/gutter and utility removal, temporary mailboxes and water outages - May 6, 2025
- 2025 Street Rehabilitation Project update about special assessment adoption and construction contract award - May 1, 2025
- 2025 Street Rehabilitation Project update about preliminary private utility work, construction beginning - April 30, 2025
- Public Hearing for the 2025 Street Rehabilitation Project set for April 22 - April 7, 2025
- 2025 Street Rehabilitation Project Update - March 6, 2025