Project Update - June 10, 2025
Below is a summary of construction activities for this week and a preview of planned work for next week. Please note schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
This Week – Week of June 9
13th Avenue and Kimberly Lane
- Reconstructing the road gravel section
11th Avenue
- Removing the existing road asphalt
10th Avenue
- Installing the storm sewer
Looking Ahead – Week of June 16
13th Avenue and Kimberly Lane
- Paving of the first layer of road asphalt
11th Avenue
- Residential connection to the temporary water system and installation of the watermain
- Water shutdown expected: Residents on 11th Avenue should expect a 10-30 minute water service interruption while the temporary water system is connected to each home. A construction representative may need to enter homes to verify the connection is functioning correctly. Homeowners will be notified in advance of any connection work.
10th Avenue
- Reconstruction of the gravel road section
Additional Information
Reminder About Driveway Access
Property owners within the construction area will continue to have access to their driveways before 7 a.m. and at the end of each workday. However, there will be times when driveway access is temporarily restricted. When this occurs, affected homeowners will be notified in advance.
We encourage residents to plan ahead and limit trips to and from their properties during construction. Thank you for your continued patience as we work to complete this project safely and efficiently.
For construction-related questions, residents can contact Dave Buganski, Plymouth’s construction representative, at dbuganski@plymouthmn.gov or 763-509-5530.
Archive of Project Update Emails
Below is a list of project update eNotify emails that have been sent to subscribers of the Frick's Garden Street Reconstruction Project. Subscribe online to receive the emails.
- Frick's Garden Reconstruction project update for the weeks of June 9 and 16 - June 10, 2025
- Frick's Garden Reconstruction project update for the weeks of June 2 and 9 - June 3, 2025
- Upcoming Mailbox Relocation for 11th Avenue - May 29, 2025
- Frick's Garden Reconstruction project update for the weeks of May 26 and June 2 - May 27, 2025
- Frick's Garden Reconstruction project update for the weeks of May 19 and 26 - May 21, 2025
- Frick's Garden Reconstruction project update for the weeks of May 12 and 19 - May 15, 2025
- Frick's Garden Reconstruction project update regarding watermain, sewer and asphalt work on 10th and 13th Avenues - May 6, 2025
- Frick's Garden Reconstruction project update regarding water system/watermain activities on 13th Ave. - April 29, 2025
- Frick's Garden Reconstruction project update regarding a delay in work due to weather - April 24, 2025
- Frick's Garden Reconstruction project update regarding temporary water systems, watermains/water outages - April 23, 2025
- Frick's Garden Reconstruction project update regarding temporary mailboxes, asphalt removal, watermains/water outages - April 15, 2025
- Frick's Garden Reconstruction project update regarding private utilities and tree removal - April 1, 2025
- Frick's Garden Reconstruction project update regarding the pre-construction meeting - March 20, 2025
- Frick's Garden Reconstruction Project Update - March 7, 2025
- Frick's Garden Reconstruction Project public meeting set for Nov. 7 - Oct. 28, 2024
- Public Meeting Scheduled for the Frick's Garden Street Reconstruction Project - Apr. 15, 2024